Requests for Proposals & Qualifications
Theatre UP Masonic Temple Building Renovation
Phase One - New Venue Project
Theatre UP Masonic Temple Building Renovation
Phase One - New Venue Project
Theatre UP will be accepting Proposals in response to the following RFPs & RFQ through March 20, 2024 at 4:00pm.
If you have any questions, please forward to Lynne Grigelevich at [email protected] no later than 4:00 PM on March 5, 2024. Answers to questions will be posted here on March 10, 2024.
If you have any questions, please forward to Lynne Grigelevich at [email protected] no later than 4:00 PM on March 5, 2024. Answers to questions will be posted here on March 10, 2024.
|
|
|
nbrc23gnh10_theatre_up_cm_rfp_addendum.pdf | |
File Size: | 40 kb |
File Type: |
Submitted Questions & Responses
- Are there any drawings of the existing building in pdf format? Existing building plans, code review, and survey attached below.
- What is the square footage of the building? 3 floors, 4,000 SF each with a partial attic.
- How was the budget of $2M determined? The budget is the money available to Theatre UP for this project.
- Is the $2M budget supposed to accommodate renovations to the Masonic Temple and the new building at 25 Ammonoosuc St? No, the budget of $2million is for the elevator and stair tower addition and renovations to the building. Renovations to include, sprinkler, addressable fire alarm, electrical upgrades, public restrooms, new HVAC system.
- Is the $2M budget inclusive of Architecture and Engineering fees? Yes, it is intended to be the total project budget.
- Have you been working with any architects in order to develop the RFP? See response below in question/response #7.
- Have you been working with any architects to develop the current life safety and accessibility upgrades to the Masonic Temple? A code analysis was completed by SFC Engineering. See pdf below.
- What is the desired schedule for design and construction of the project? Design to commence after hiring of the A&E team. We hope to start construction by late fall, 2024.
- Can you also confirm that certified payroll and/or Davis-Bacon wage rates will not be required on this project? We have been told that the NBRC grant does not require Davis Bacon or certified payroll.
- Please provide a list of items that you want each of your CM’s to include in their general conditions estimate. Please see the attached Gen Con-CM Fee matrix.
masonic_temple_existing_conditions.pdf | |
File Size: | 10052 kb |
File Type: |
sfc_code_report_-_littleton_masonic_temple_feasibility_study_2021_1124.pdf | |
File Size: | 341 kb |
File Type: |
temple_survey_update_1.12.24.pdf | |
File Size: | 323 kb |
File Type: |
t-up_fee-gen_con_matrix.pdf | |
File Size: | 51 kb |